We have carried out extensive inspections and studies, repair planning, and repairs for the chimneys and flue gas channels of the Nevel Forssa power plant and heating centers. The projects were planned well in advance and executed in collaboration with the client. This approach has always led to positive outcomes
Nevel Forssa

Hyvinkään Lämpövoima Oy has relied on our comprehensive services for years.
Hyvinkään Lämpövoima Oy

We carried out the safety measures for the decommissioned massive brick chimney of the former power plant in Kuusankoski under winter conditions. Although the project was challenging, the work was completed on schedule and in good collaboration with the client’s representative.
UPM

For years, we have been conducting inspections of the chimneys and ducts of the heating plants in Kajaani in collaboration with the client. Together with the client’s representative, we have developed follow-up action plans for steel repair work and protective painting, taking into account the client’s changing future plans
Loiste Lämpö Oy

Comprehensive inspection and research work on the concrete chimneys of Ruskeasuo and Myllypuro. Repair planning and repairs.
Helen Oy
Google Oy /
Enso-Gutzeit Oy
We carried out a highly demanding comprehensive demolition of a 136-meter-high brick chimney. The chimney was located in the middle of the factory area, with electrical transformers in its immediate vicinity.
Google Oy / Enso-Gutzeit Oy

From 2009 to 2022, we conducted inspections, repair planning, and various repair projects for the client’s brick, steel, and fiberglass chimneys. Our objectives in the repair work were set according to the client’s requirements.
Laanilan Voima Oy
Stora Enso Imatran ja Sunilan tehtaat
From 2018 to 2022, we have carried out extensive steel, brick, and concrete repair works, as well as partial demolition work. In addition to the chimneys and flue gas ducts, the scope of the repair work has also involved other buildings within the facility. Some of the repair and demolition work was performed during the winter under very challenging conditions
Stora Enso Imatran ja Sunilan tehtaat
Hiedanrannan Kehitys Oy
The repair work on the protected, decommissioned chimney of the former M-Real factory in Tampere involved dismantling and reconstructing the chimney, along with other comprehensive repair tasks. Between 2021 and 2022, demolition work and preparations for the repairs were carried out. After the demolition, the chimney was raised back to its original height using a new innovation, and TPH utilized its own brick production for the masonry. The masonry work was performed at ground level during the winter of 2022–2023, and the finished masonry pieces, approximately two meters high and designed to mimic the shape and appearance of the chimney, were lifted one by one and installed in place. This repair project was the most challenging in TPH’s history, as the impacts of the pandemic and the war in Ukraine significantly slowed down the work. The project timeline was extended due to these reasons. The client and the client’s representatives contributed to the schedule, and the project was completed in the spring of 2023.
Hiedanrannan Kehitys Oy

In the summer of 2024, we carried out repair work on the fiberglass chimney at the Inkoo plant. Alternative repair methods were considered, but it was decided to lower the chimney to ground level, where the repair work was carried out according to the repair plan we had prepared. The biggest challenge before the repair work was obtaining reliable information about the structural integrity and the condition of the inside of the chimney.
NMC Termonova Oy

We have carried out extensive inspections and studies, repair planning, repairs, and demanding demolition work on the potassium sulfate chimney at Yara Kokkola between 2022 and 2024. The projects have been very challenging and required significant planning efforts prior to execution. They were implemented in close cooperation with the client’s representatives.
Yara